High risk
  • Possession delayed ~1 yr. Originally promised Apr 2025, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 72.7%.
Satellite view of this address

Where it is · 29/1/1 Alandi devachi, Alandi Devachi

Promoter

Builder profile

Builder
LUNKAD VISHWA DEVELOPER

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
GL DESIGNS

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100045975
Status
New
Stage
Certificate Signed
Possession
July 2026originally April 2025
Construction
72.7% complete
Units sold
58 of 81

Similar projects in Alandi Devachi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Alandi Devachi compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.