High risk
  • Possession delayed ~1 yr. Originally promised Mar 2024, now proposed Jun 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 90.9%.

Area guide

What it's like to buy in KURLA

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Roha Realty Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
DESIGN ARCHITECTS AND INTERIOR DESIGNERS

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800029480
Status
New
Stage
Certificate Signed
Possession
June 2025originally March 2024
Construction
90.9% complete
Units sold
122 of 166

Similar projects in KURLA

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how KURLA compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.