Under construction
ROYAL LAGOON E WING
MahaRERA P51800026297High risk
CTS No. 6A/16, Borivali, 400095
Post your property hereOwn or renting out a unit in ROYAL LAGOON E WING? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Borivali come to you.
Apr 2027
Possession
35%
Built
0
Complaints
202
Units
High risk
- Behind schedule. Possession is due Apr 2027 but construction is only at 35%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address
Where it is · CTS No. 6A/16, Borivali
Area guide
What it's like to buy in Borivali
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
RIKKI RONIE DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800026297
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2026
- Construction
- 35% complete
- Units sold
- 89 of 202
Similar projects in Borivali
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
DPS AISHWARYA
BorivaliPoss. December 20274 complaints
LAXMI MADHUVAN
BorivaliPoss. September 2027
ATULYA
BorivaliPoss. April 2027
JALARAM SQUARE
BorivaliPoss. January 20281 complaint
Sixty 3 W.E. Bizpark
BorivaliPoss. October 2031
GRACE BUSINESS PLAZA
BorivaliPoss. April 2030
AVVIRAHI PLATINUM
BorivaliPoss. April 2031
THRISH9
BorivaliPoss. April 2031
Keep exploring
Where this project sits, who built it, and how Borivali compares.
In Borivali
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.