Under construction

ROYAL RESIDENCY

MahaRERA P52000011059High risk

by Royal Enterprises

Survey no 32, Hissa No2A,CTS No 2236, TAKAI, 410203

Official record
Jul 2027
Possession
45.2%
Built
0
Complaints
133
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2024, now proposed Jul 2027 per the RERA filing.
  • Behind schedule. Possession is due Jul 2027 but construction is only at 45.2%.
Satellite view of this address

Where it is · Survey no 32, Hissa No2A,CTS No 2236, TAKAI

Area guide

What it's like to buy in TAKAI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Royal Enterprises

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000011059
Status
Ongoing
Stage
Certificate Signed
Possession
July 2027originally March 2024
Construction
45.2% complete
Units sold
35 of 133

Keep exploring

Where this project sits, who built it, and how TAKAI compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.