Under construction
ROYAL RESIDENCY
MahaRERA P99000047035High risk
C.T.S. NO. 1100, 1102, 1103, 1104, 1105, VASAI, 401201
Post your property hereOwn or renting out a unit in ROYAL RESIDENCY? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in VASAI come to you.
Dec 2025
Possession
89.5%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised Aug 2024, now proposed Dec 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 89.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.
Satellite view of this address
Where it is · C.T.S. NO. 1100, 1102, 1103, 1104, 1105, VASAI
Promoter
Builder profile
SKYLINE SHELTERS
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
KANCHAN ARUN PATIL
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P99000047035
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025originally August 2024
- Construction
- 89.5% complete
- Units sold
- 0 of 0
Similar projects in VASAI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
DEEP SKY F WING
VASAIPoss. December 2028
AAI CHANDIKA HILLS
VASAI99.9% builtPoss. September 2026
CANARY-WING C
VASAI91% builtPoss. July 2027
KAILASH TOWER
VASAI90.9% builtPoss. December 20245 complaints
ORNATE HEIGHTS PHASE I
VASAI90.5% builtPoss. February 2027
BLOSSOM
VASAI88.4% builtPoss. April 2028
ASMI ENCLAVE
VASAI86.4% builtPoss. April 2027
SOLITAIRE HIGHWAY
VASAI81.8% builtPoss. December 2018
Keep exploring
Where this project sits, who built it, and how VASAI compares.
In VASAI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.