Under construction
RUCHA VATIKA TULIP C WING
MahaRERA P51700018987High risk
by MILAN HOUSING COMPLEX PVT. LTD.
189, TITWALA EAST, 421605
Post your property hereOwn or renting out a unit in RUCHA VATIKA TULIP C WING? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in TITWALA EAST come to you.
Dec 2021
Possession
52.7%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 52.7%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2021 per the RERA filing.
Area guide
What it's like to buy in TITWALA EAST
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
MILAN HOUSING COMPLEX PVT. LTD.
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700018987
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2021
- Construction
- 52.7% complete
- Units sold
- 0 of 0
Similar projects in TITWALA EAST
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
CHARMS PARADISE C WING
TITWALA EAST90.9% builtPoss. March 2018
CHARMS PARK PHASE 1
TITWALA EAST90.9% builtPoss. March 2018
SHREE NANDAN PARK B WING
TITWALA EAST80.9% builtPoss. December 2024
GANPATI PRASANNA
TITWALA EAST77.3% builtPoss. December 2026
DATTARAM TOWER
TITWALA EAST40.9% builtPoss. August 2027
Keep exploring
Where this project sits, who built it, and how TITWALA EAST compares.
In TITWALA EAST
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.