RUSTOMJEE AZZIANO WING E
by Kapstone Constructions Private Limited
49/1,2,3 50/1A,2,3 51/1,2,3,4PT,5PT 53/2/3 383PT, Thane, 400601
- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession date passed. The proposed possession date (Feb 2023) has passed with construction at 90%.
- Promised amenities not started. Gymnasium, Landscaped Garden, Sports / Jogging are at 0% build with possession due Feb 2023 per the RERA filing.
Where it is · 49/1,2,3 50/1A,2,3 51/1,2,3,4PT,5PT 53/2/3 383PT, Thane
Area guide
What it's like to buy in Thane
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700015260
- Status
- New
- Stage
- Certificate Signed
- Possession
- February 2023
- Construction
- 90% complete
- Units sold
- 0 of 0
Similar projects in Thane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Thane compares.
In Thane
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.