Rustomjee Summit
CTS No 88 Pt, Rajendra Nagar, 400066
- Litigation pending (8). MahaRERA's litigation disclosure lists 8 pending cases against this project.
- 5 appeals at MahaREAT. 5 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~6 yrs. Originally promised Dec 2021, now proposed Dec 2027 per the RERA filing.
- 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
Where it is · CTS No 88 Pt, Rajendra Nagar
Area guide
What it's like to buy in Rajendra Nagar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Self-sufficient Gujarati-dominated family belt beside the National Park.
- Growth drivers:
- Metro 2A/7, station upgrades, big-brand township launches.
- Who buys here:
- Families seeking space and community at sane prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800003590
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2021
- Construction
- 90.6% complete
- Units sold
- 0 of 233
Similar projects in Rajendra Nagar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Rajendra Nagar compares.
In Rajendra Nagar
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 30 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.