- Possession delayed ~2 yrs. Originally promised Apr 2026, now proposed Apr 2028 per the RERA filing.
Where it is · 67/1D, SHILL
Area guide
What it's like to buy in SHILL
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700032338
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2028originally April 2026
- Construction
- 58.9% complete
- Units sold
- 72 of 264
Similar projects in SHILL
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how SHILL compares.
In SHILL
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.