Sabari Palm View
CTS NO 1746 BY 13, Kurla, 400071
- Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 92.7%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2019 per the RERA filing.
Where it is · CTS NO 1746 BY 13, Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800001155
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2019
- Construction
- 92.7% complete
- Units sold
- 0 of 0
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.