High risk
  • Possession delayed ~1 yr. Originally promised Dec 2020, now proposed Jun 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 10%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2022 per the RERA filing.
Satellite view of this address

Where it is · S.NO. 34/3A , YEWALEWADI PUNE -411048, YEWALEWADI

Area guide

What it's like to buy in YEWALEWADI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
YOGESH OMPRAKASH AGARWAL

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100005445
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally December 2020
Construction
10% complete
Units sold
0 of 0

Similar projects in YEWALEWADI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how YEWALEWADI compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.