Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Aug 2026 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO 85, PUSHPAK NAGAR, NAVI MUMBAI

Area guide

What it's like to buy in PUSHPAK NAGAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
ANMOL BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
RAJESH RC

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000034601
Status
New
Stage
Certificate Signed
Possession
August 2026originally December 2024
Construction
81.6% complete
Units sold
5 of 18

Keep exploring

Where this project sits, who built it, and how PUSHPAK NAGAR, NAVI MUMBAI compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.