High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 36.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · S NO 13 HNO 1, MACCHA PADA

Area guide

What it's like to buy in MACCHA PADA

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SAIRAJDEVELOP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
B A C PLANNERS AND ENGINEERS PVT LTD

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700012717
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally December 2024
Construction
36.4% complete
Units sold
96 of 108