🏗️
Under construction

SAI KRUPA VALLEY- PHASE 1

MahaRERA P52000000739Caution

by SAI KRUPA DEVELOPERS

neral village new survey no 4891-29, Neral, 410101

Official record
Aug 2026
Possession
92.4%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Aug 2026) has passed with construction at 92.4%.
Satellite view of this address

Where it is · neral village new survey no 4891-29, Neral

Area guide

What it's like to buy in Neral

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SAI KRUPA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000000739
Status
Ongoing
Stage
Certificate Signed
Possession
August 2026originally August 2025
Construction
92.4% complete
Units sold
0 of 0

Similar projects in Neral

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Neral compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.