Under construction
SAI KUBER PROJECT
MahaRERA P51600077676High risk
by SAI KUBER BUILDERS AND DEVELOPERS
PLOT NO 3 SURVEY NO 49(48)/7/A/2, DESHWANDI, 422103
Post your property hereOwn or renting out a unit in SAI KUBER PROJECT? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in DESHWANDI come to you.
Apr 2027
Possession
33.6%
Built
0
Complaints
15
Units
High risk
- Behind schedule. Possession is due Apr 2027 but construction is only at 33.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address
Where it is · PLOT NO 3 SURVEY NO 49(48)/7/A/2, DESHWANDI
Area guide
What it's like to buy in DESHWANDI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SAI KUBER BUILDERS AND DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600077676
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2026
- Construction
- 33.6% complete
- Units sold
- 0 of 15
Keep exploring
Where this project sits, who built it, and how DESHWANDI compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.