Under construction
Sai Manas
MahaRERA P52000008081High risk
by Sai Smaran infra and Developers
151/17A, Pashane, 410201
Post your property hereOwn or renting out a unit in Sai Manas? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Pashane come to you.
Oct 2026
Possession
49.1%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~8 yrs. Originally promised Dec 2018, now proposed Oct 2026 per the RERA filing.
- Behind schedule. Possession is due Oct 2026 but construction is only at 49.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Satellite view of this address
Where it is · 151/17A, Pashane
Promoter
Builder profile
Sai Smaran infra and Developers
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000008081
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2026originally December 2018
- Construction
- 49.1% complete
- Units sold
- 0 of 0
Similar projects in Pashane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
TULSI AASHRAY
Pashane90.9% builtPoss. September 2018
GURUDEV PARK
Pashane90.9% builtPoss. May 2022
HIMALAYA GARDENS
Pashane90.9% builtPoss. October 20231 complaint
SHIV UTSAV
Pashane86.9% builtPoss. March 2025
DEEPJYOTI CITY
Pashane85.4% builtPoss. March 2028
HIMALAYA COMPLEX
Pashane84.1% builtPoss. September 2018
DHRUV RESIDENCY PHASE EXCELLENCY KWING
Pashane81.8% builtPoss. December 2018
HIMALAYA GARDENS
Pashane75.8% builtPoss. March 2027
Keep exploring
Where this project sits, who built it, and how Pashane compares.
In Pashane
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.