Under construction

SAI PLAZA

MahaRERA P52100011700Caution

by SHREE DEVELOPERS

25/6,25/6/7,25/6/7/2,25/8,25/9/8,25/9/9, AMBEGAON Bk, 411046

Official record
Sept 2022
Possession
74.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 74.5%.
Satellite view of this address

Where it is · 25/6,25/6/7,25/6/7/2,25/8,25/9/8,25/9/9, AMBEGAON Bk

Promoter

Builder profile

Builder
SHREE DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100011700
Status
Ongoing
Stage
Certificate Signed
Possession
September 2022
Construction
74.5% complete
Units sold
0 of 0

Similar projects in AMBEGAON Bk

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how AMBEGAON Bk compares.