Under construction

Sai Proviso County

MahaRERA P51700002042High risk

by Proviso Builders and Developers

154/1 New Survey No.399/132 to 399/137, 399/147, 399/148, 399/148 A, 399/170, 399/171, 162/3, 154/3, Panvel, 410221

Official record
Dec 2023
Possession
84%
Built
4
Complaints
0
Units
High risk
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~3 yrs. Originally promised Jun 2021, now proposed Dec 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 84%.
Satellite view of this address

Where it is · 154/1 New Survey No.399/132 to 399/137, 399/147, 399/148, 399/148 A, 399/170, 399/171, 162/3, 154/3, Panvel

Area guide

What it's like to buy in Panvel

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Proviso Builders and Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700002042
Status
Ongoing
Stage
Certificate Signed
Possession
December 2023originally June 2021
Construction
84% complete
Units sold
0 of 0

Similar projects in Panvel

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Panvel compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.