  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · S NO 77 H NO 3, DEVRUND

Promoter

Builder profile

Builder
SAI RAM BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
BHARGAV SURESH JOSHI

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700076874
Status
New
Stage
Certificate Signed
Possession
April 2027originally March 2025
Construction
83% complete
Units sold
20 of 115