High risk
  • Possession delayed ~3 yrs. Originally promised Apr 2019, now proposed Oct 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 81.8%.
Satellite view of this address

Where it is · 96, Navlakh Umbre

Promoter

Builder profile

Builder
S.R. DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100012266
Status
Ongoing
Stage
Certificate Signed
Possession
October 2021originally April 2019
Construction
81.8% complete
Units sold
0 of 0