High risk
  • 16 appeals at MahaREAT. 16 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~8 yrs. Originally promised Dec 2019, now proposed Dec 2027 per the RERA filing.
  • 104 RERA complaints. 104 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · 77 AND 78, Mulshi

Promoter

Builder profile

Builder
PRAKASH PANDURANG CHAVAN

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100003410
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2019
Construction
73.6% complete
Units sold
0 of 0

Similar projects in Mulshi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mulshi compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.