Under construction

Saisparsh

MahaRERA P52100047216High risk

by MEGHSPARSH ASSOCIATES A

5563,5563/1, 5564, 5564/1 to 5, 5565, 5566, 5570, 5570/1, 5571, 5571/1 to 4, 5579, 5580, 5580/1,to 4,5581,5582,5583,5584,5584/1 to 4, 5557, 5561 & 5562 Pimpri, Kharalwadi, 411018

Official record
Dec 2025
Possession
70%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 70%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Promoter

Builder profile

Builder
MEGHSPARSH ASSOCIATES A

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100047216
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
70% complete
Units sold
0 of 0

Similar projects in Kharalwadi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kharalwadi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.