Under construction

SAMARTH PLAZA APARTMENT

MahaRERA P51600009652High risk

by SHREE SAMARTH BUILDERS AND DEVELOPERS

332/3/1A/3 AND 4 PLOT NO 3 AND 4, Nashik (M Corp.), 422009

Official record
Jun 2023
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2020, now proposed Jun 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 332/3/1A/3 AND 4 PLOT NO 3 AND 4, Nashik (M Corp.)

Promoter

Builder profile

Builder
SHREE SAMARTH BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51600009652
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally December 2020
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Nashik (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Nashik (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 12 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.