High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession date passed. The proposed possession date (Oct 2023) has passed with construction at 11.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2023 per the RERA filing.

Promoter

Builder profile

Builder
SANKALP REALTY

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000020734
Status
New
Stage
Certificate Signed
Possession
October 2023
Construction
11.8% complete
Units sold
0 of 0

Similar projects in SECTOR 5A

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how SECTOR 5A compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.