High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2021, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 70%.
Satellite view of this address

Where it is · SURVEY NO 28 H NO 2, Vasai

Promoter

Builder profile

Builder
JAMALUDDIN HIMAYATALI SHAIKH

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000011761
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally June 2021
Construction
70% complete
Units sold
0 of 0

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.