Sara Heights
G No 47, Hissa No. 19 and 20, At Manjarli Badlapur, 421503
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Apr 2027 per the RERA filing.
- Behind schedule. Possession is due Apr 2027 but construction is only at 45.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Where it is · G No 47, Hissa No. 19 and 20, At Manjarli Badlapur
Area guide
What it's like to buy in At Manjarli Badlapur
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The value frontier beyond Kalyan — low-rise affordability, improving rail links.
- Growth drivers:
- Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
- Who buys here:
- First-home buyers stretching every rupee.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51700015758
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2022
- Construction
- 45.2% complete
- Units sold
- 26 of 115
Keep exploring
Where this project sits, who built it, and how At Manjarli Badlapur compares.
In At Manjarli Badlapur
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.