High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~4 yrs. Originally promised Dec 2019, now proposed Nov 2023 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Nov 2023) has passed with construction at 90.9%.
  • Promised amenities not started. Gymnasium is at 0% build with possession due Nov 2023 per the RERA filing.
Satellite view of this address

Where it is · 831 -PT, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
RRB REALTORS PVT LTD.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800000726
Status
Ongoing
Stage
Certificate Signed
Possession
November 2023originally December 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.