Under construction
Savitri Enclave
MahaRERA P52000034933High risk
by Savitri Builders and Developer
Plot No.- 97, Pushpak, 410206
Post your property hereOwn or renting out a unit in Savitri Enclave? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Pushpak come to you.
Apr 2027
Possession
49.1%
Built
0
Complaints
47
Units
High risk
- Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Apr 2027 per the RERA filing.
- Behind schedule. Possession is due Apr 2027 but construction is only at 49.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address
Where it is · Plot No.- 97, Pushpak
Promoter
Builder profile
Savitri Builders and Developer
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000034933
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2025
- Construction
- 49.1% complete
- Units sold
- 14 of 47
Similar projects in Pushpak
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
S R HARI OM
PushpakPoss. April 2028
Excel Polaris
PushpakPoss. October 2029
Sai Imperia
PushpakPoss. December 2027
Om Sai Vaastu
PushpakPoss. April 2028
Riddhi Siddhi Angan
PushpakPoss. April 2031
Ideal Residency
PushpakPoss. April 2031
Altamontt One
PushpakPoss. June 2029
World Tower
PushpakPoss. September 2029
Keep exploring
Where this project sits, who built it, and how Pushpak compares.
In Pushpak
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.