SDPL Aashray Godhani
Plot No. 6, Kh. No. 130/1,130/2, Godhani, 441123
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 93.3%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2026 per the RERA filing.
Where it is · Plot No. 6, Kh. No. 130/1,130/2, Godhani
Area guide
What it's like to buy in Godhani
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P50500030259
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026
- Construction
- 93.3% complete
- Units sold
- 0 of 0
Similar projects in Godhani
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Godhani compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.