High risk
  • 4 appeals at MahaREAT. 4 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 90.5%.
Satellite view of this address

Where it is · SURVEY NO 53/6 VILL NAVGHAR, Mira-Bhayandar (M Corp.)

Area guide

What it's like to buy in Mira-Bhayandar (M Corp.)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Dahisar / Mira RoadValue

The city's northern value frontier, densifying fast.

Growth drivers:
Metro 9 extension, spillover from Borivali pricing.
Who buys here:
First-time buyers stretching for a 1–2 BHK.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
AAKASH BUILDERS & DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700011846
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally December 2019
Construction
90.5% complete
Units sold
0 of 0

Similar projects in Mira-Bhayandar (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mira-Bhayandar (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.