High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Possession delayed ~6 yrs. Originally promised Dec 2018, now proposed Dec 2024 per the RERA filing.
  • 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 54.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.
Satellite view of this address

Where it is · 2,2a,11,12,13,14,15,16,17, Thane

Area guide

What it's like to buy in Thane

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Navi Mumbai (Vashi–Nerul)Mid-income

Planned-city order — wide roads, node markets, established social infra.

Growth drivers:
Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
Who buys here:
Professionals wanting planned-city living with airport-corridor upside.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Sanjeev Vasant Divekar

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700005875
Status
Ongoing
Stage
Certificate Signed
Possession
December 2024originally December 2018
Construction
54.5% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.