Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2028 per the RERA filing.
Satellite view of this address

Where it is · Final Plot No 7 & 8, TPS - 01, TPS Naina

Promoter

Builder profile

Builder
M/s PALMS QUALITY CONSTRUCTION REALTY LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
An. Arch Architect & Planner

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52000052102
Status
New
Stage
Certificate Signed
Possession
April 2028originally December 2027
Construction
31.8% complete
Units sold
56 of 125

Keep exploring

Where this project sits, who built it, and how TPS Naina compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.