High risk
  • Possession delayed ~1 yr. Originally promised Dec 2021, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 59.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO 24A, SECTOR 53,DRONAGIRI, Uran

Area guide

What it's like to buy in Uran

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
MAVERICK DEVELOPERS DRONAGIRI

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000009481
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally December 2021
Construction
59.9% complete
Units sold
0 of 0

Similar projects in Uran

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Uran compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.