High risk
  • Possession delayed ~4 yrs. Originally promised Jul 2024, now proposed Jul 2028 per the RERA filing.
Satellite view of this address

Where it is · 939 PART, KHOPOLI

Promoter

Builder profile

Builder
MAINCO REALTY LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000017716
Status
New
Stage
Certificate Signed
Possession
July 2028originally July 2024
Construction
62.3% complete
Units sold
0 of 0