High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Oct 2027 per the RERA filing.
Satellite view of this address

Where it is · 19 A/1 Pt and 25A, Borivali

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
AAKASH DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Pankaj Biyani

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800027166
Status
New
Stage
Certificate Signed
Possession
October 2027originally June 2024
Construction
90.9% complete
Units sold
110 of 115

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.