Under construction

SHAMBHAVI GOLD

MahaRERA P52100076875Caution

by N K COMPANY

Gat no 849 to 854, plot no -17, Gat no 849. to 855, 412207

Official record
Dec 2027
Possession
31.8%
Built
0
Complaints
24
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Area guide

What it's like to buy in Gat no 849. to 855

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
N K COMPANY

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100076875
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
31.8% complete
Units sold
2 of 24

Keep exploring

Where this project sits, who built it, and how Gat no 849. to 855 compares.

Data sourced from the official MahaRERA portal; complaints last synced 5 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.