High risk
  • Possession delayed ~6 yrs. Originally promised Aug 2021, now proposed Apr 2027 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · 51/3, Wafe

Promoter

Builder profile

Builder
Shubha Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
ASHISH VAIDHYA

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51700009534
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally August 2021
Construction
71.4% complete
Units sold
105 of 154

Keep exploring

Where this project sits, who built it, and how Wafe compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.