Under construction
SHAURYA RESIDENCE
MahaRERA P52100005749High risk
SR NO 1, H. NO. 1/1, 1/2, 2, 3, 4, 5/2, 6/1, 8/1, 8/2, 9/1, CHIRKE COLONY, 411047
Post your property hereOwn or renting out a unit in SHAURYA RESIDENCE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in CHIRKE COLONY come to you.
Aug 2027
Possession
97%
Built
1
Complaints
175
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Aug 2027 per the RERA filing.
- Promised amenities not started. Clubhouse is at 0% build with possession due Aug 2027 per the RERA filing.
Satellite view of this address
Where it is · SR NO 1, H. NO. 1/1, 1/2, 2, 3, 4, 5/2, 6/1, 8/1, 8/2, 9/1, CHIRKE COLONY
Promoter
Builder profile
3 S PROPERTIES
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100005749
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- August 2027originally December 2023
- Construction
- 97% complete
- Units sold
- 168 of 175
Keep exploring
Where this project sits, who built it, and how CHIRKE COLONY compares.
In CHIRKE COLONY
The developer
Research