Under construction

SHEETAL TAPOVAN

MahaRERA P51800011437High risk

by DGS TOWNSHIP PVT LTD

818 823A 823B 823C 823 1 818, Borivali, 400097

Official record
Dec 2026
Possession
93.6%
Built
13
Complaints
273
Units
High risk
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Dec 2026 per the RERA filing.
  • 13 RERA complaints. 13 complaint records are disclosed against this project on MahaRERA.

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
DGS TOWNSHIP PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
RASIK HINGOO

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800011437
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally June 2023
Construction
93.6% complete
Units sold
264 of 273

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.