SHETH ZURI
by Sheth Developers Private Limited
OUT OF SURVEY NO 85/1P, 81/1A, 83/2, 83/5, 85/2, 85/3, 85/4P, 85/5, Thane, 400601
- Mortgaged to a lender (₹75 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹75 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- 14 appeals at MahaREAT. 14 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
- 68 RERA complaints. 68 complaint records are disclosed against this project on MahaRERA.
Where it is · OUT OF SURVEY NO 85/1P, 81/1A, 83/2, 83/5, 85/2, 85/3, 85/4P, 85/5, Thane
Area guide
What it's like to buy in Thane
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700007274
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 94.2% complete
- Units sold
- 706 of 717
Similar projects in Thane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Thane compares.
In Thane
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.