Under construction

SHIV KRUPA COMPLEX

MahaRERA P99000022459High risk

by SHREE RADHE CONSTRUCTION

SURVEY NO 120 HISSA NO 6 PT, SURBEY NO 120 HISSA. NO 9, Vasai, 401209

Official record
Dec 2027
Possession
23.7%
Built
0
Complaints
197
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 120 HISSA NO 6 PT, SURBEY NO 120 HISSA. NO 9, Vasai

Area guide

What it's like to buy in Vasai

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SHREE RADHE CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000022459
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
23.7% complete
Units sold
10 of 197

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.