High risk
  • Possession delayed ~3 yrs. Originally promised May 2018, now proposed Nov 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Nov 2020) has passed with construction at 39.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2020 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 29 , HISSA NO 7 AND 8A, Kalyan

Promoter

Builder profile

Builder
KRUTIKA BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700008806
Status
Ongoing
Stage
Certificate Signed
Possession
November 2020originally May 2018
Construction
39.1% complete
Units sold
0 of 0

Similar projects in Kalyan

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kalyan compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.