High risk
  • Possession date passed. The proposed possession date (Mar 2021) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2021 per the RERA filing.
Satellite view of this address

Where it is · GAT NO 60, NEAR MOSHI TOLL PLAZA

Promoter

Builder profile

Builder
SHIVKAILAS DEVELOPMENT CORPORATION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100023537
Status
New
Stage
Certificate Signed
Possession
March 2021originally December 2020
Construction
81.8% complete
Units sold
0 of 0