High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 88.5%.
Satellite view of this address

Where it is · 532 D, Borivali

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SAMARTH ERECTORS & DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800006063
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
88.5% complete
Units sold
0 of 0

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.