High risk
  • Possession delayed ~1 yr. Originally promised Jan 2024, now proposed Jun 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 90.9%.

Area guide

What it's like to buy in Bhamburda Shivajinagar

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Kotibhaskar Infrastructures &Developers Pvt.Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100030056
Status
New
Stage
Certificate Signed
Possession
June 2025originally January 2024
Construction
90.9% complete
Units sold
0 of 0