Under construction

SHRADDHA AUTUMN PARK

MahaRERA P51800007651High risk

by ATHARVA DEVELOPERS

1050 1051 PT 1052 1053 AND 1058, Kurla, 400042

Official record
Dec 2027
Possession
85.3%
Built
1
Complaints
0
Units
High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~6 yrs. Originally promised Dec 2021, now proposed Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · 1050 1051 PT 1052 1053 AND 1058, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Bhandup / KanjurmargMid-income

Emerging eastern corridor between Powai and Mulund.

Growth drivers:
Metro 6 (JVLR), large land parcels turning into townships.
Who buys here:
Value-hunters betting on the corridor's growth.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
ATHARVA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800007651
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2021
Construction
85.3% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.