Official record
Apr 2027
Possession
1.6%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 1.6%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.

Promoter

Builder profile

Builder
SHREE LAXMI REALTY

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700055452
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
1.6% complete
Units sold
0 of 0

Similar projects in SUNIL NAGAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how SUNIL NAGAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.