🏗️
Under construction
SHREE CHINMAY GAURANG GRIHSANKUL
MahaRERA P52000004925Caution
by SHREE CHINMAY GAURANG INFRASTRUCTURE
FINAL PLOT NO. 263, URAN NAKA, PANVEL, PANVEL, 410206
Post your property hereOwn or renting out a unit in SHREE CHINMAY GAURANG GRIHSANKUL? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in PANVEL come to you.
Sept 2020
Possession
90.9%
Built
1
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.9%.
Satellite view of this address
Where it is · FINAL PLOT NO. 263, URAN NAKA, PANVEL, PANVEL
Promoter
Builder profile
SHREE CHINMAY GAURANG INFRASTRUCTURE
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000004925
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2020
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in PANVEL
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Nexspace, Godrej City, Panvel
PANVELPoss. April 2033
Tower 5, Green Terraces, Godrej City, Panvel
PANVELPoss. September 20331 complaint
SUSHEEL ANANT
PANVELPoss. April 2030
Golf Crest, Godrej City, Panvel
PANVELPoss. December 2033
MARATHON NEXZONE ACRUX -1
PANVEL100% builtPoss. December 20215 complaints
Balaji Symphony phase 2
PANVEL100% builtPoss. December 202044 complaints
Balaji Symphony
PANVEL100% builtPoss. December 201853 complaints
OM NAMAH SHIVAY KALASH
PANVEL100% builtPoss. March 20181 complaint
Keep exploring
Where this project sits, who built it, and how PANVEL compares.
In PANVEL
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.