High risk
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 0%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2024 per the RERA filing.

Promoter

Builder profile

Builder
S.S. CONSTRUCTION AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100050818
Status
New
Stage
Certificate Signed
Possession
March 2024
Construction
0% complete
Units sold
0 of 0

Similar projects in MOHAN NAGAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how MOHAN NAGAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.