High risk
  • Possession delayed ~1 yr. Originally promised Mar 2026, now proposed Jul 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.

Area guide

What it's like to buy in DAHISAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SHRI RANCHHODJI REAL DEVELOPRS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
CREATIVE CONSULTANTS & DESIGNERS

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800055912
Status
New
Stage
Certificate Signed
Possession
July 2027originally March 2026
Construction
65.9% complete
Units sold
0 of 18

Similar projects in DAHISAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how DAHISAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.